Thor Main Replacement

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Over the past several years, SSWD has developed a mechanism to identify water mains that have a high risk of failure (leaks!). During some of our most recent analysis, we identified the Arden Park Unit No. 2 subdivision as having one of the highest risk rates in the District.  This discovery lead our engineering team to begin planning the replacement of the water mains in the subdivision to ensure customers continue to receive reliable water supplies with minimal disruptions. The project, named the Thor Water Main Replacement Project, consists of the installation of new water distribution main pipeline in public streets to replace existing backyard water mains that have outlived their useful life.

Major project facts:

  • 16,000 feet of 6-, 8-, and 12-inch diameter pipe is to be installed
  • 50 fire hydrants will be upgraded
  • 200 new metered services will be installed; and 7 meters will be reconnected
  • The construction cost is estimated to be $5.8 million

Schedule:

  • Pre-construction activities began early in March 2020 and the project was completed in late 2020.
  • Final street restoration will begin in the spring of 2021 (warmer temperatures are necessary for this type of work).

Thor Main Replacement Project with Hydrants

 

Download the pdf version of the project area map

 

Main Replacement FAQs.

Billing:

  • Flat rate billing will remain in effect until November 2021 when it will convert to meter rate billing.
  • Shortly after your meter is installed, your water bill will include new informational items:
    • A consumption graph showing monthly usage.
    • Meter rate billing amount.
  • You may opt to start meter rate billing early.  If so, please contact the Customer Service Department at 916.972.7171 or email feedback@sswd.org.            

Water Meter Facts and FAQs.

 

Contact Information:

After-hours emergency calls should be directed to SSWD's main number 916.972.7171.

Construction Manager (primary contact)
      ERC Contracting (contractor for SSWD)
      Ricky (Richard) Ingraham
      Phone: 916.768.0786
      Email: erccontracting@yahoo.com

Field Inspector
      S. E. Ahlstrom Inspection (contractor for SSWD)
      Scott Ahlstrom
      Phone: 916.849.7159
      Email: seahlstorm@yahoo.com

Project Manager
      Sacramento Suburban Water District
      David Espinoza, P.E.
      Phone: 916.679.2886
      Email: despinoza@sswd.org